MRG Goody Storage
50.4 MW storage in Lamar, TX · In queue since May 2022 · Proposed COD March 2026
50.4 MW
Capacity
1
Components
Battery
4 years
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 6m
IA → COD
2y 4m
Total Duration
1y 6m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-03-20
The MRG Goody Storage project is a proposed 50.4 MW battery storage project located in Lamar County, Texas. The developer is MRG Goody Solar Project LLC. It is interconnected within the ERCOT region under queue ID ERCOT-24INR0305, with a queue entry date of May 10, 2022, and a proposed commercial operation date of March 20, 2026.
The project's Interconnection Agreement (IA) has been executed as of November 7, 2023. The Point of Interconnection (POI) is Tap 138 kV Toco Switch (#1700) _x0013_ Paris Switch (#1693). The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
MRG Goody Solar Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Toco Switch (#1700) _x0013_ Paris Switch (#1693)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.