Burro Loco Energy Storage
25.14 MW storage in Cameron, TX · In queue since July 2022 · Proposed COD September 2028
25.14 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-15
The Burro Loco Energy Storage project is a proposed 25.14 MW battery storage project located in Cameron County, Texas. Developed by VESI, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0319, with a queue entry date of July 18, 2022.
The proposed commercial operation date for the Burro Loco Energy Storage project is September 15, 2028. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the 8626 Resaca 69kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
VESI
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8626 Resaca 69kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Burro Loco Energy Storage