XE Murat Storage
60.14 MW storage in Harris, TX · In queue since June 2022 · Proposed COD May 2025
60.14 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 5m
IA → COD
1y 6m
Total Duration
1y 5m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-05-05
The XE Murat Storage project is a proposed 60.14 MW battery storage project located in Harris County, Texas. The project, developed by Liberty 1 Solar LLC, is interconnected within the Electric Reliability Council of Texas (ERCOT) queue as entry ERCOT-24INR0329, with a queue entry date of June 2, 2022. The proposed commercial operation date is May 5, 2025.
The project's Interconnection Agreement (IA) has been executed as of November 1, 2023. The point of interconnection (POI) is the 138 kV CROSBY C66(#40391) -ATASCOCITA (#40130) Line, managed by CNP. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Liberty 1 Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap the 138 kV CROSBY C66(#40391) -ATASCOCITA (#40130) Line; CNP
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.