Eldora Solar
200.94 MW generation in Matagorda, TX · In queue since June 2022 · Proposed COD July 2028
200.94 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 5m
IA → COD
4y 8m
Total Duration
1y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-07-02
Eldora Solar is a proposed 200.94 MW solar generation project located in Matagorda County, Texas. The project is being developed by Eldora Energy LLC and is interconnected within the Electric Reliability Council of Texas (ERCOT) queue as entry ERCOT-24INR0337, with a queue entry date of June 10, 2022. The proposed commercial operation date is July 2, 2028.
The project's interconnection agreement (IA) was executed on November 15, 2023. Eldora Solar has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Eldora Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 5915 South Texas Project _x0013_ 44200 Hillje Ckt 1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- 1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Eldora Solar