Forts Trail BESS
200.93 MW storage in Taylor, TX · In queue since June 2022 · Proposed COD July 2028
200.93 MW
Capacity
1
Components
Battery
3y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-25
The Forts Trail BESS project is a proposed 200.93 MW battery storage project located in Taylor County, Texas. Developed by JC Central Bluff, LLC, the project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-24INR0341 on June 2, 2022. The proposed commercial operation date is July 25, 2028, and the project's interconnection status is currently in the Facility Study phase.
The Forts Trail BESS project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Taylor
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
JC Central Bluff, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11406 Central Bluff Switch 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Central
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Forts Trail BESS