Exodus Solar
181.02 MW generation in Caldwell, TX · In queue since June 2022 · Proposed COD May 2026
181.02 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 11m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
Exodus Solar is a proposed 181.02 MW solar generation project located in Caldwell County, Texas. The project, developed by Exodus Solar LLC, is in the ERCOT interconnection queue as entry ERCOT-24INR0353, with a queue entry date of June 10, 2022. The proposed commercial operation date is May 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection is Tap 345kV 7040 Austrop _x0013_ 7042 Zorn. The Exodus Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Caldwell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Exodus Solar LLC.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 7040 Austrop _x0013_ 7042 Zorn
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Exodus Solar