Anatole Renewable Energy Storage
207.82 MW storage in Henderson, TX · In queue since June 2022 · Proposed COD March 2027
207.82 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Status
Signed May 2024
Queue → IA
1y 11m
IA → COD
2y 10m
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-03-31
The Anatole Renewable Energy Storage project is a proposed 207.82 MW battery storage project located in Henderson County, Texas. The developer is Eustace Storage LLC. It is interconnected within the ERCOT region under queue ID ERCOT-24INR0355, with a queue entry date of June 2, 2022, and a proposed commercial operation date of March 31, 2027.
The project's Interconnection Agreement (IA) has been executed as of May 10, 2024. The point of interconnection is the Eustace Southeast 138kV Substation (Bus# 6951), owned by Rayburn Electric Cooperative.
Generated from interconnection queue and public data sources
State
TX
County
Henderson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Eustace Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
(Bus# 6951) Eustace Southeast 138kV Substation (owned by Rayburn Electric Cooperative)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Southeast Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.