Pitts Dudik II
30.23 MW generation in Hill, TX · In queue since July 2022 · Proposed COD April 2026
30.23 MW
Capacity
1
Components
Solar
3y 10m
In Queue
IA Executed
IA Status
Signed Jun 2024
Queue → IA
1y 11m
IA → COD
1y 10m
Total Duration
1y 11m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-04-24
Pitts Dudik II is a proposed solar generation project with a total capacity of 30.23 MW, located in Hill County, Texas. The project is being developed by Pitts Dudik II and is interconnected within the Electric Reliability Council of Texas (ERCOT) region. It entered the ERCOT interconnection queue as project number ERCOT-24INR0364 on July 18, 2022, with a proposed commercial operation date of April 24, 2026.
The project's Interconnection Agreement (IA) has been executed as of June 13, 2024. The Point of Interconnection (POI) is the 138 kV Ash Creek Switch (#3473).
Generated from interconnection queue and public data sources
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pitts Dudik II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Ash Creek Switch (#3473)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.