Glory Bee Solar
305 MW generation in Erath, TX · In queue since June 2022 · Proposed COD April 2026
305 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 10m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-14
The proposed Glory Bee Solar project is a 305 MW solar generation facility under development by Riley Solar LLC in Erath County, Texas. The project is located within the Electric Reliability Council of Texas (ERCOT) region and is listed in the ERCOT interconnection queue as entry ERCOT-24INR0368, with a queue entry date of June 10, 2022.
The project's proposed commercial operation date is April 14, 2026. Its interconnection status is currently in the Facility Study phase. The point of interconnection is planned at the Tap 345kV 1440 Comanche Switch - 1900 Comanche Peak.
Generated from interconnection queue and public data sources
State
TX
County
Erath
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Riley Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1440 Comanche Switch - 1900 Comanche Peak
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Comanche
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.