GIGA AUSTIN SOLAR
— generation in Travis, TX · In queue since July 2022 · Proposed COD March 2027
—
Capacity
0
Components
3y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-14
The GIGA AUSTIN SOLAR project is a proposed solar generation facility with a total capacity that is not specified in the data. It is located in Travis County, Texas, and is being developed by GIGA TEXAS ENERGY LLC. The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0372, with a queue entry date of July 18, 2022.
The proposed commercial operation date (COD) for the GIGA AUSTIN SOLAR project is March 14, 2027. Its interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is the 7047 HORNSBY Substation at 138kV. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Travis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
GIGA TEXAS ENERGY LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7047 HORNSBY Substation 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- GIGA_ESS_RN
- POI Substation
- Hornsby Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.