Solara BESS 1 (ERCOT-24INR0378) — Project Summary

Queue ID
ERCOT-24INR0378
Capacity
150 MW
Technology
Battery
Status
active
Location
Jones, TX
Region
ERCOT
Developer
CED Development Inc.
IA Status
Facility Study

Solara BESS 1

ERCOT-24INR0378BetaActiveBatteryERCOTLBNL + Live

150 MW storage in Jones, TX · In queue since July 2022 · Proposed COD November 2027

150 MW

Capacity

1

Components

Battery

3y 10m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

5y 4m

Facilities Study50%
Queue EntryJul 5, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-30

About

The Solara BESS 1 project is a proposed 150 MW battery storage project located in Jones County, Texas. Developed by CED Development Inc., the project is currently in the ERCOT interconnection queue as entry ERCOT-24INR0378, with a queue entry date of July 5, 2022. The proposed commercial operation date is November 30, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.

The project consists entirely of battery storage, with a total capacity of 150 MW. The point of interconnection is the 60387 Hendrick 138kV location. The Solara BESS 1 project has appeared in recent news coverage regarding energy storage developments in Texas.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Jones

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

CED Development Inc.

Utility

Entity

ERCOT

Service Type

Point of Interconnection

60387 Hendrick 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Solara BESS 1