Photo BESS 3
100 MW storage in Uvalde, TX · In queue since July 2022 · Proposed COD September 2027
100 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
Photo BESS 3 is a proposed 100 MW battery storage project located in Uvalde County, Texas. The project, developed by CED Development Inc., is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-24INR0380 on July 25, 2022. The proposed commercial operation date is September 1, 2027, and the project's interconnection status is currently in the Facility Study phase.
The development has been mentioned in recent news coverage. The project consists of 100 MW of battery storage capacity.
Generated from interconnection queue and public data sources
State
TX
County
Uvalde
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5885 Downie Substation 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HELIOS_RN
- POI Substation
- Downie Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Photo BESS 3