Remy Jade III Power Station
102 MW generation in Harris, TX · In queue since July 2022 · Proposed COD May 2028
102 MW
Capacity
1
Components
Gas
3y 10m
In Queue
IA Executed
IA Status
Signed Aug 2022
Queue → IA
1 month
IA → COD
5y 9m
Total Duration
1 month
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2028-05-01
The Remy Jade III Power Station is a proposed 102 MW gas-fired generation project located in Harris County, Texas. Developed by Remy Jade III Generating, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0382. The project entered the interconnection queue on July 18, 2022, with a proposed commercial operation date of May 1, 2028. The Interconnection Agreement (IA) for the project was executed on August 1, 2022.
The Remy Jade III Power Station has been the subject of recent news coverage, with nine articles related to the project appearing in industry and grid publications. The point of interconnection is Tap 138kV 40390 Crosby - 40811 Highlands.
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Remy Jade III Generating, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 40390 Crosby - 40811 Highlands
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CS_RN
- POI Substation
- Crosby Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26