100.9 MW generation in Brazoria, TX · In queue since January 2023
100.9 MW
Capacity
1
Components
Solar
3y 4m
In Queue
—
IA Status
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Long Point Solar II is a proposed 100.9 MW solar generation project located in Brazoria County, Texas. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0390, with a queue entry date of January 17, 2023. Its status is currently listed as suspended.
The development project consists of 100.9 MW of solar capacity. No proposed commercial operation date or interconnection agreement (IA) status is available. The developer is not specified in the provided data. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Long Point Solar II