ELECTRODE BESS
150 MW storage in Upton, TX · In queue since July 2022 · Proposed COD December 2027
150 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The ELECTRODE BESS project is a proposed 150 MW battery storage project located in Upton County, Texas. Developed by CED Development Inc., the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0393, with a queue entry date of July 25, 2022.
The proposed commercial operation date for ELECTRODE BESS is December 31, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Castillo Substation, Bus number 76040.
Generated from interconnection queue and public data sources
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Castillo Substation, Bus number : 76040
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about ELECTRODE BESS