CATHODE BESS
150 MW storage in Upton, TX · In queue since August 2022 · Proposed COD December 2027
150 MW
Capacity
1
Components
Battery
3y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The CATHODE BESS project is a proposed 150 MW battery storage project located in Upton County, Texas. Developed by CED Development Inc., the project entered the ERCOT interconnection queue as queue ID ERCOT-24INR0394 on August 5, 2022. The current proposed commercial operation date is December 31, 2027, and the project's interconnection status is currently in the Facility Study phase.
The CATHODE BESS project has been mentioned in recent news coverage related to deals and industry developments.
Generated from interconnection queue and public data sources
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76635 King Mountain 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SPTX12B_RN
- POI Substation
- King Mountain Southwest Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14