Destiny Storage (ERCOT-24INR0397) — Project Summary

Queue ID
ERCOT-24INR0397
Capacity
205.57 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
Destiny Storage, LLC
IA Status
IA Executed

Destiny Storage

ERCOT-24INR0397BetaActiveBatteryERCOTLBNL + Live

205.57 MW storage in Harris, TX · In queue since August 2022 · Proposed COD May 2026

205.57 MW

Capacity

1

Components

Battery

3y 9m

In Queue

IA Executed

IA Status

Signed Sep 2023

Interconnection

Queue → IA

1y 1m

IA → COD

2y 8m

Total Duration

1y 1m

Construction75%
Queue EntryAug 16, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementSep 20, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-05-20

About

Destiny Storage is a proposed 205.57 MW battery storage project located in Harris County, Texas. The project, developed by Destiny Storage, LLC, is interconnected within the ERCOT region under queue ID ERCOT-24INR0397. The project entered the queue on August 16, 2022, and has a proposed commercial operation date of May 20, 2026. The interconnection agreement (IA) for the project was executed on September 20, 2023.

The proposed project is linked to the existing Destiny Storage operating plant (EIA ID 67654). Recent news coverage indicates the project has been the subject of at least four articles, primarily related to deals.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Harris

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Destiny Storage, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 40390 Crosby - 40680 Placid Ckt 86

Data Source

LBNL + Live

DeveloperCypress Creek RenewablesEnergy-Storage.News · 2025-03-13
TransactionDebt financingEnergy-Storage.News · 2025-03-13
Deal value$133.0MEnergy-Storage.News · 2025-03-13
LenderFirst Citizens BankEnergy-Storage.News · 2025-03-13
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
MEDIUM
Nearest Node (Estimated)
HOUSTON

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Destiny Storage