Tres Rios Ranch Solar
508 MW generation in Upton, TX · In queue since August 2022 · Proposed COD December 2027
508 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The Tres Rios Ranch Solar project is a proposed 508 MW solar generation facility in Upton County, Texas. Developed by LectricWind LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0404, with a queue entry date of August 5, 2022. The proposed commercial operation date is December 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 76008 Twelvemile 345kV location. The Tres Rios Ranch Solar project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
LectricWind LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76008 Twelvemile 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.