NRG Greens Bayou 6 (ERCOT-24INR0410) — Project Summary

Queue ID
ERCOT-24INR0410
Capacity
445 MW
Technology
Gas
Status
active
Location
Harris, TX
Region
ERCOT
Developer
NRG Texas Power
IA Status
Facility Study

NRG Greens Bayou 6

ERCOT-24INR0410BetaActiveGasERCOTLBNL + Live

445 MW generation in Harris, TX · In queue since August 2022 · Proposed COD May 2028

445 MW

Capacity

1

Components

Gas

3y 9m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

5y 9m

Facilities Study50%
Queue EntryAug 16, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

About

The NRG Greens Bayou 6 project is a proposed 445 MW gas-fired generation project located in Harris County, Texas. The developer is NRG Texas Power. It is interconnected within the ERCOT region under queue ID ERCOT-24INR0410, with an interconnection queue entry date of August 16, 2022. The proposed commercial operation date is May 1, 2028, and the interconnection agreement status is currently in the Facility Study phase.

The project is linked to the existing Greens Bayou operating plant (EIA plant ID 3464). Recent news coverage of the project includes topics such as deals, hazards, industry, and grid issues.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Harris

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

NRG Texas Power

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Position 1/0 PSSE 40710, Greens Bayou Substation, 138 kV

Data Source

LBNL + Live

DeveloperNRG EnergyUtility Dive · 2025-11-21
TransactionProject financingUtility Dive · 2025-11-21
Deal value$370.0MUtility Dive · 2025-11-21
LenderTexas Energy FundUtility Dive · 2025-11-21
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
HIGH
Nearest Node (Estimated)
GBY_GT
POI Substation
Greens Bayou 69kV Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26