Greens Bayou Unit 9 CT 345 (ERCOT-24INR0411) — Project Summary

Queue ID
ERCOT-24INR0411
Capacity
455 MW
Technology
Gas
Status
active
Location
Harris, TX
Region
ERCOT
Developer
NRG Texas Power LLC
IA Status
Facility Study

Greens Bayou Unit 9 CT 345

ERCOT-24INR0411BetaActiveGasERCOTLBNL

455 MW generation in Harris, TX · In queue since September 2022 · Proposed COD June 2026

455 MW

Capacity

1

Components

Gas

3y 8m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

3y 9m

Facilities Study50%
Queue EntrySep 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-02

About

The proposed Greens Bayou Unit 9 CT 345 project is a 455 MW gas-fired generation project located in Harris County, Texas. Developed by NRG Texas Power LLC, the project entered the ERCOT interconnection queue on September 21, 2022, with queue ID ERCOT-24INR0411. The proposed commercial operation date is June 2, 2026.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Greens Bayou Substation.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Harris

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

NRG Texas Power LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Position 1/0 PSSE 40700, Greens Bayou Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.