Camino Ranch Solar SLF
296.42 MW generation in Houston, TX · In queue since October 2022 · Proposed COD December 2028
296.42 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-09
The Camino Ranch Solar SLF project is a proposed solar generation facility with a total capacity of 296.42 MW. Located in Houston County, Texas, the project is being developed by Camino Ranch Solar Project LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0412, with a queue entry date of October 6, 2022. The proposed commercial operation date is December 9, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists solely of solar generation, with the entire 296.42 MW capacity attributed to solar photovoltaic technology. The point of interconnection is planned at the Tap to Jim English (#3351) _x0013_ Flat Branch (#3345) 138kV. The project has appeared in recent news coverage regarding energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Houston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Camino Ranch Solar Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap to Jim English (#3351) _x0013_ Flat Branch (#3345) 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Camino Ranch Solar SLF