Trelas
200.83 MW storage in Mcculloch, TX · In queue since September 2022 · Proposed COD May 2028
200.83 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
The proposed Trelas project is a 200.83 MW battery storage development in McCulloch County, Texas. The project, developed by Trelasol, LLC, is located within the ERCOT region and consists entirely of battery storage.
The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0416, with a queue entry date of September 2, 2022. Its proposed commercial operation date is May 1, 2028, and its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 76006 Bow Wood 345kV Bus.
Generated from interconnection queue and public data sources
State
TX
County
Mcculloch
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Trelasol, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76006 Bow Wood 345kV Bus
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Bow Wood Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.