Camino Ranch Storage SLF
298.06 MW storage in Houston, TX · In queue since October 2022 · Proposed COD December 2028
298.06 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-09
The Camino Ranch Storage SLF project is a proposed 298.06 MW battery storage project located in Houston County, Texas. Developed by Camino Solar Ranch, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0420, with a queue entry date of October 18, 2022. The proposed commercial operation date is December 9, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists solely of battery storage, with a total capacity of 298.06 MW. The point of interconnection is Tap to Jim English (#3351) _x0013_ Flat Branch (#3345) 138kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Houston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Camino Solar Ranch, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap to Jim English (#3351) _x0013_ Flat Branch (#3345) 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.