CPS AvR CT1 Rotor Replacement (ERCOT-24INR0427) — Project Summary

Queue ID
ERCOT-24INR0427
Capacity
11.3 MW
Technology
Gas
Status
active
Location
Bexar, TX
Region
ERCOT
Developer
CPS Energy
IA Status
Facility Study

CPS AvR CT1 Rotor Replacement

ERCOT-24INR0427BetaActiveGasERCOTLBNL + Live

11.3 MW generation in Bexar, TX · In queue since October 2022 · Proposed COD March 2026

11.3 MW

Capacity

1

Components

Gas

3y 7m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

3y 5m

Schedule

1 months past proposed COD

Facilities Study50%
Queue EntryOct 24, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-28

About

The CPS AvR CT1 Rotor Replacement is a proposed 11.3 MW gas-fired generation project located in Bexar County, Texas. Developed by CPS Energy, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0427, with a queue entry date of October 24, 2022. The proposed commercial operation date is March 28, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.

The project involves a gas-fired generator with a capacity of 11.3 MW. The point of interconnection is the 5475 Braunig 345kV substation.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Bexar

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

CPS Energy

Utility

Entity

ERCOT

Service Type

Point of Interconnection

5475 Braunig 345kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
BRA_AVR1_CT2
POI Substation
Braunig Switchyard

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about CPS AvR CT1 Rotor Replacement