Umbra Solar II
344.66 MW generation in Franklin, TX · In queue since June 2023
344.66 MW
Capacity
1
Components
Solar
2y 11m
In Queue
—
IA Status
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Umbra Solar II is a proposed solar generation project with a total capacity of 344.66 MW, located in Franklin County, Texas. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0437, with a queue entry date of June 28, 2023. The project's status is currently listed as suspended.
The development is located within the ERCOT region. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
TX
County
Franklin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.