PSE Minnesota TX Storage (ERCOT-24INR0448) — Project Summary

Queue ID
ERCOT-24INR0448
Capacity
94 MW
Technology
Battery
Status
active
Location
Hidalgo, TX
Region
ERCOT
Developer
PureSky Development Inc
IA Status
Facility Study

PSE Minnesota TX Storage

ERCOT-24INR0448BetaActiveBatteryERCOTLBNL + Live

94 MW storage in Hidalgo, TX · In queue since November 2022 · Proposed COD June 2028

94 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

5y 7m

Facilities Study50%
Queue EntryNov 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

About

The PSE Minnesota TX Storage project is a proposed 94 MW battery storage project located in Hidalgo County, Texas. Developed by PureSky Development Inc., the project entered the ERCOT interconnection queue as entry ERCOT-24INR0448 on November 15, 2022. The current interconnection status is Facility Study, with a proposed commercial operation date of June 30, 2028.

The project consists of 94 MW of battery storage capacity. The point of interconnection is Tap 138kV 8372 North Pharr _x0013_ 8906 North Alamo. The project is currently listed as active in the ERCOT interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hidalgo

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

PureSky Development Inc

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 8372 North Pharr _x0013_ 8906 North Alamo

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about PSE Minnesota TX Storage