Longfellow Solar II
207.36 MW generation in Pecos, TX · In queue since November 2022 · Proposed COD June 2027
207.36 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
Longfellow Solar II is a proposed solar generation project with a total capacity of 207.36 MW, located in Pecos County, Texas. The project is being developed by Century Gas Processing, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0454, with a queue entry date of November 7, 2022.
The proposed commercial operation date for Longfellow Solar II is June 30, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 38432 TNCENTRY2_1 138 KV.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CENTURY GAS PROCESSING, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38432 TNCENTRY2_1 138 KV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.