FRIENDSWOOD ENERGY GENCO
143.7 MW generation in Harris, TX · In queue since December 2022 · Proposed COD March 2026
143.7 MW
Capacity
1
Components
Gas
3y 5m
In Queue
IA Executed
IA Status
Signed Apr 2024
Queue → IA
1y 4m
IA → COD
1y 11m
Total Duration
1y 4m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2026-03-21
The Friendswood Energy Genco project is a proposed 143.7 MW gas-fired generation project located in Harris County, Texas. The project is being developed by Tejas Power Generation LLC. It entered the ERCOT interconnection queue as queue ID ERCOT-24INR0456 on December 7, 2022, with a proposed commercial operation date of March 21, 2026. The project's interconnection agreement (IA) was executed on April 23, 2024.
The proposed project is linked to the existing Friendswood Energy operating plant (EIA plant ID 60468). The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tejas Power Generation LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
47170 H O CLARKE 138KV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- FEGC RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26