Hooper Solar
50.48 MW generation in Lee, TX · In queue since December 2022 · Proposed COD December 2027
50.48 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
The Hooper Solar project is a proposed 50.48 MW solar generation facility in Lee County, Texas. The project, developed by BT Brown Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0473, with a queue entry date of December 7, 2022. The proposed commercial operation date is December 15, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 138kV line between Lexington (Bus #7571) and Lyle Wolz (Bus #7567). The Hooper Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Lee
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Brown Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV line between Lexington (Bus #7571) and Lyle Wolz (Bus #7567)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Lexington
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hooper Solar