NRG THW GT 138 (ERCOT-24INR0479) — Project Summary

Queue ID
ERCOT-24INR0479
Capacity
458 MW
Technology
Gas
Status
active
Location
Harris, TX
Region
ERCOT
Developer
NRG THW GT LLC
IA Status
Facility Study

NRG THW GT 138

ERCOT-24INR0479BetaActiveGasERCOTLBNL

458 MW generation in Harris, TX · In queue since November 2022 · Proposed COD June 2026

458 MW

Capacity

1

Components

Gas

3y 6m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

3y 7m

Facilities Study50%
Queue EntryNov 22, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-05

About

The proposed NRG THW GT 138 project is a 458 MW gas-fired generation project located in Harris County, Texas. The developer is NRG THW GT LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0479, with a queue entry date of November 22, 2022. The project's proposed commercial operation date is June 5, 2026, and its interconnection agreement status is currently in the Facility Study phase.

The point of interconnection for the project is the 138 kV Bus Number 45515, named T_H_W__POI_8.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Harris

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

NRG THW GT LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

138 kV Bus Number: 45515, Bus Name: T_H_W__POI_8

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.