Forts Trail BESS 2
201.2 MW storage in Taylor, TX · In queue since February 2023 · Proposed COD July 2028
201.2 MW
Capacity
1
Components
Battery
3y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-25
The Forts Trail BESS 2 project is a proposed 201.2 MW battery storage project located in Taylor County, Texas. The developer is JC Central Bluff, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0488, with a queue entry date of February 20, 2023, and a proposed commercial operation date of July 25, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 201.2 MW of battery storage. The point of interconnection is the 11406 Central Bluff Switch 345 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Taylor
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
JC Central Bluff, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11406 Central Bluff Switch 345 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Central
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Forts Trail BESS 2