Indigo Storage
60 MW storage in Fisher, TX · In queue since December 2022 · Proposed COD September 2027
60 MW
Capacity
1
Components
Battery
3y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-17
Indigo Storage is a proposed 60 MW battery storage project located in Fisher County, Texas. The developer is Innovative Solar 245, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0496, with a queue entry date of December 15, 2022, and a proposed commercial operation date of September 17, 2027. Its interconnection status is currently in the Facility Study phase.
The proposed project consists of 60 MW of battery storage capacity. Recent news coverage indicates industry interest in the development.
Generated from interconnection queue and public data sources
State
TX
County
Fisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Innovative Solar 245, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 68001 Claytonville _x0013_ 68004 Phantom Hill Circuit 2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Indigo Storage