Medina Lake BESS
9.8 MW storage in Bandera, TX · In queue since November 2022 · Proposed COD June 2025
9.8 MW
Capacity
1
Components
Battery
3y 6m
In Queue
IA Executed
IA Status
Signed Jan 2023
Queue → IA
2 months
IA → COD
2y 5m
Total Duration
2 months
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-06-14
The Medina Lake BESS project is a proposed 9.8 MW battery storage project located in Bandera County, Texas. Developed by Regis Medina Lake LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0499. The project entered the interconnection queue on November 29, 2022, and has a proposed commercial operation date of June 14, 2025.
The project's Interconnection Agreement (IA) has been executed as of January 18, 2023.
Generated from interconnection queue and public data sources
State
TX
County
Bandera
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Regis Medina Lake LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Station Name (TDSP Station Code) MEDILA; Load/Load Transformer Name T2; PTI BUS number 7432; Voltage in kV (Transmission Level) 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Medina Lake BESS