Corralitos Wind 2 (ERCOT-24INR0506) — Project Summary

Queue ID
ERCOT-24INR0506
Capacity
195.4 MW
Technology
Wind
Status
active
Location
Zapata, TX
Region
ERCOT
Developer
Vaquero Wind Energy, LLC
IA Status
Facility Study

Corralitos Wind 2

ERCOT-24INR0506BetaActiveWindERCOTLBNL + Live

195.4 MW generation in Zapata, TX · In queue since January 2023 · Proposed COD December 2027

195.4 MW

Capacity

1

Components

Wind

3y 4m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

4y 11m

Facilities Study50%
Queue EntryJan 30, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

About

Corralitos Wind 2 is a proposed 195.4 MW wind generation project located in Zapata County, Texas. The developer is Vaquero Wind Energy, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0506, with a queue entry date of January 30, 2023. The proposed commercial operation date is December 31, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C at the New ETT Tiempo Substation.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Zapata

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Vaquero Wind Energy, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation)

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.