Young Wind II SLF
152.28 MW generation in Young, TX · In queue since May 2023 · Proposed COD March 2026
152.28 MW
Capacity
1
Components
Wind
3 years
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2y 10m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-08
The Young Wind II SLF project is a proposed wind generation facility with a total capacity of 152.28 MW. Located in Young County, Texas, the project is being developed by Young Wind II, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0507, with a queue entry date of May 3, 2023, and a proposed commercial operation date of March 8, 2026. The project's interconnection status is currently in the Facility Study phase, and it is slated to connect to Oncor's Thomas Price Station (#11523).
The Young Wind II SLF project has been the subject of recent news coverage, with two articles categorized as regulatory and industry news.
Generated from interconnection queue and public data sources
State
TX
County
Young
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Young Wind II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Oncor's Thomas Price Station (#11523)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.