Timber Cove Solar SLF
100.5 MW generation in Freestone, TX · In queue since May 2023 · Proposed COD April 2027
100.5 MW
Capacity
1
Components
Solar
3 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
Timber Cove Solar SLF is a proposed 100.5 MW solar generation project located in Freestone County, Texas. Developed by Freestone Solar, LLC, the project consists of 100.5 MW of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-24INR0532, with a queue entry date of May 22, 2023, and a proposed commercial operation date of April 1, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Timber Cove Solar operating plant (EIA plant ID 66922). The point of interconnection is Tap 138 kV 212 Winkler - 3510 Pin Oak. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Freestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Freestone Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV 212 Winkler - 3510 Pin Oak
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FREC
- POI Substation
- Richland Chambers Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.