Padua Grid BESS Unit 2
150.94 MW storage in Bexar, TX · In queue since June 2023 · Proposed COD March 2026
150.94 MW
Capacity
1
Components
Battery
2y 11m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
2y 9m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-03-31
Padua Grid BESS Unit 2 is a proposed 150.94 MW battery storage project in Bexar County, Texas. Developed by Padua Grid, LLC, the project consists of a single 150.94 MW battery component. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0533, with a queue entry date of June 7, 2023, and a proposed commercial operation date of March 31, 2026. The project's interconnection agreement has been executed.
The proposed project is linked to the existing Padua 2 operating plant (EIA plant ID 68913). Recent news coverage indicates that the project has been mentioned in at least four news articles, primarily related to deals.
Generated from interconnection queue and public data sources
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Padua Grid, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5395 Sommers 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- RN_PAD3_ESS
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26