Thomas Cameron BESS
201.52 MW storage in Lampasas, TX · In queue since June 2023 · Proposed COD May 2027
201.52 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-03
The Thomas Cameron BESS project is a proposed 201.52 MW battery storage project located in Lampasas County, Texas. Developed by Thomas Cameron BESS LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0543, with a queue entry date of June 7, 2023, and a proposed commercial operation date of May 3, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCH. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Lampasas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Thomas Cameron BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCH
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Thomas Cameron BESS