Shaula I BESS
86.88 MW storage in Dewitt, TX · In queue since July 2023 · Proposed COD December 2025
86.88 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
2y 5m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The Shaula I BESS project is a proposed 86.88 MW battery storage project located in Dewitt County, Texas. Developed by Shaula Energy Project LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0555, with a queue entry date of July 10, 2023. The proposed commercial operation date is December 31, 2025, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 86.88 MW of battery storage capacity. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Dewitt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Shaula Energy Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5380 Shaula 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Shaula I BESS