Texas Bluebonnet Solar
9.72 MW generation in Mclennan, TX · In queue since May 2023 · Proposed COD February 2025
9.72 MW
Capacity
1
Components
Solar
3 years
In Queue
IA Executed
IA Status
Signed Aug 2023
Queue → IA
3 months
IA → COD
1y 6m
Total Duration
3 months
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-02-07
Texas Bluebonnet Solar is a proposed 9.72 MW solar generation project located in McLennan County, Texas. The project, developed by Texas Bluebonnet Solar Partners, LLC, is interconnected within the ERCOT region under queue ID ERCOT-24INR0580. The project entered the interconnection queue on May 26, 2023, with a proposed commercial operation date of February 7, 2025.
The interconnection agreement for Texas Bluebonnet Solar was executed on August 28, 2023. The point of interconnection is the 3370 McGuffey POD 138 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Mclennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Texas Bluebonnet Solar Partners, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3370 McGuffey POD 138 kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Texas Bluebonnet Solar