16.1 MW generation in Wharton, TX · In queue since July 2023 · Proposed COD March 2025
16.1 MW
Capacity
1
Components
Gas
2y 10m
In Queue
IA Executed
IA Status
Signed Mar 2022
IA → COD
3 years
Total Duration
2y 10m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2025-03-27
The TEXAS GULF SULPHUR REPOWER project is a proposed 16.1 MW gas-fired generation project located in Wharton County, Texas. The developer is Wharton County Generation, LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-24INR0605, with a queue entry date of July 31, 2023, and a proposed commercial operation date of March 27, 2025.
The project has an Interconnection Agreement (IA) executed as of March 1, 2022. The point of interconnection is the 43340 Gulftie 138 kV substation. The project is linked to an existing operating plant. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Wharton County Generation, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
43340 Gulftie 138 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.