Rodeo Ranch Energy Storage Repowering
10 MW storage in Reeves, TX · In queue since August 2023 · Proposed COD February 2025
10 MW
Capacity
1
Components
Battery
2y 9m
In Queue
IA Executed
IA Status
Signed Feb 2022
IA → COD
3 years
Total Duration
2y 9m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-02-07
The Rodeo Ranch Energy Storage Repowering project is a proposed 10 MW battery storage project located in Reeves County, Texas. The project, developed by Rodeo Ranch Energy Storage, LLC, is interconnected within the ERCOT region under queue ID ERCOT-24INR0609. The project entered the queue on August 22, 2023, with a proposed commercial operation date of February 7, 2025.
The project's Interconnection Agreement (IA) has been executed as of February 1, 2022. The point of interconnection (POI) is the 38021 WORSHAM 138kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rodeo Ranch Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38021 WORSHAM 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WRSBES_BESS1
- POI Substation
- Worsham Field Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.