GridGuardian BESS (ERCOT-24INR0616) — Project Summary

Queue ID
ERCOT-24INR0616
Capacity
227.99 MW
Technology
Battery
Status
active
Location
Bell, TX
Region
ERCOT
Developer
SMT Temple BESS LLC
IA Status
Facility Study

GridGuardian BESS

ERCOT-24INR0616BetaActiveBatteryERCOTLBNL

227.99 MW storage in Bell, TX · In queue since September 2023 · Proposed COD April 2027

227.99 MW

Capacity

1

Components

Battery

2y 8m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 7m

Facilities Study50%
Queue EntrySep 22, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-19

About

GridGuardian BESS is a proposed 227.99 MW battery storage project located in Bell County, Texas. The project, developed by SMT Temple BESS LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0616, with a queue entry date of September 22, 2023. The proposed commercial operation date is April 19, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.

The project consists entirely of battery storage, with a total capacity of 227.99 MW. The point of interconnection is the 3412 TEMPLE PECAN CREEK 345kV substation. The GridGuardian BESS project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Bell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

SMT Temple BESS LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

3412 TEMPLE PECAN CREEK 345kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
BELM_SLR_RN
POI Substation
Temple Pecan Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.