Anemoi Energy Storage Repowering
5 MW storage in Hidalgo, TX · In queue since October 2023 · Proposed COD February 2025
5 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
1y 4m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-02-28
The Anemoi Energy Storage Repowering project is a proposed 5 MW battery storage project located in Hidalgo County, Texas. Developed by Anemoi Energy Storage, LLC, the project entered the ERCOT interconnection queue as queue ID ERCOT-24INR0636 on October 30, 2023. Its proposed commercial operation date is February 28, 2025, and its interconnection status is currently in the Facility Study phase.
The project consists of a single 5 MW battery component. The point of interconnection is the 8574 POMELO 345kV substation. The project is listed as active in the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Hidalgo
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anemoi Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8574 POMELO 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ANEM_ESS_RN
- POI Substation
- Pomelo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Anemoi Energy Storage Repowering