Team Ranch Storage
307.2 MW storage in Tarrant, TX · In queue since June 2024 · Proposed COD March 2027
307.2 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
The Team Ranch Storage project is a proposed 307.2 MW battery energy storage system located in Tarrant County, Texas. Developed by BAF Storage, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0763, with a queue entry date of June 13, 2024. The proposed commercial operation date is March 1, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 307.2 MW of battery storage. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Tarrant
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BAF Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1869 Benbrook Switch 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.