Tokyo TxHSR TPSS EW-1
50 MW generation in Ellis, TX · In queue since January 2019 · Proposed COD July 2028
50 MW
Capacity
1
Components
Other
7y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
9y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-15
The Tokyo TxHSR TPSS EW-1 project is a proposed 50 MW generation project located in Ellis County, Texas. The project, developed by Texas Central Rail Holdings, LLC, utilizes an "Other" technology type. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0005, with a queue entry date of January 30, 2019.
The proposed commercial operation date (COD) for the project is July 15, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is at the tap 138kV 2241 Ennis W - 2321 Waxahachie.
Generated from interconnection queue and public data sources
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Texas Central Rail Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 2241 Ennis W - 2321 Waxahachie
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Ennis Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Tokyo TxHSR TPSS EW-1