Nockenut Springs Solar 3
203.39 MW generation in Gonzales, TX · In queue since September 2020 · Proposed COD June 2029
203.39 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-05
The Nockenut Springs Solar 3 project is a proposed solar generation facility with a total capacity of 203.39 MW. It is located in Gonzales County, Texas, and is being developed by Pecan Springs Energy, LLC. The project is currently active in the ERCOT interconnection queue under queue ID ERCOT-25INR0010, with an interconnection queue entry date of September 25, 2020.
The proposed commercial operation date for Nockenut Springs Solar 3 is June 5, 2029. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 345kV 5133 Elm Creek - 5915 STP ckt 1.
Generated from interconnection queue and public data sources
State
TX
County
Gonzales
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pecan Springs Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 5133 Elm Creek - 5915 STP ckt 1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Elm Creek Substation