Yellow Cat Wind
301.2 MW generation in Navarro, TX · In queue since August 2021 · Proposed COD April 2027
301.2 MW
Capacity
1
Components
Wind
4y 9m
In Queue
IA Executed
IA Status
Signed Jul 2024
Queue → IA
2y 11m
IA → COD
2y 9m
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-04-01
Yellow Cat Wind is a proposed 301.2 MW wind generation project located in Navarro County, Texas. The developer is Yellow Cat Wind LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-25INR0018, with an interconnection queue entry date of August 17, 2021. The proposed commercial operation date is April 1, 2027.
The project's Interconnection Agreement (IA) has been executed as of July 9, 2024. The point of interconnection (POI) is Tap 345kV 1906 Venus - 68091 Navarro. The Yellow Cat Wind project has been the subject of recent news coverage, with six articles related to industry developments and deals.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Yellow Cat Wind LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1906 Venus - 68091 Navarro
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DSWL_BES1
- POI Substation
- Venus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.