Itsee Solar
52.9 MW generation in Navarro, TX · In queue since October 2021 · Proposed COD July 2027
52.9 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
The Itsee Solar project is a proposed 52.9 MW solar generation facility located in Navarro County, Texas. The project, developed by Gransolar Texas Seventeen, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0024, with a queue entry date of October 12, 2021.
The proposed commercial operation date for Itsee Solar is July 1, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Trinidad Switch and Long Prairie Switch 138 kV line.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Seventeen, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Trinidad Switch _x0013_ Long Prairie Switch 138 kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Itsee Solar