Borderland ESC
200 MW storage in Hidalgo, TX · In queue since February 2022 · Proposed COD November 2028
200 MW
Capacity
1
Components
Battery
4y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-30
The Borderland ESC project is a proposed 200 MW battery storage project located in Hidalgo County, Texas. Developed by FRESH AIR ENERGY II, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0039, with a queue entry date of February 21, 2022.
The proposed commercial operation date for the Borderland ESC project is November 30, 2028. The project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
TX
County
Hidalgo
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
FRESH AIR ENERGY II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 8380 NEDIN4A _x0013_ 8632 NMCALLEN4C
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Borderland ESC